Plan adjustment examples

In this example, the old single plan must be updated according to a new schedule that contains two planned requirements:

Schedule Requirement date Requirement quantity RAN Type
Old single plan 11/17/yyyy 80 RAN001 Firm
11/17/yyyy 90 RAN002 Firm
11/19/yyyy 90 RAN003 Firm
11/20/yyyy 120 Planned
11/25/yyyy 130 Planned
New schedule 11/21/yyyy 100 Planned
11/24/yyyy 120 Planned
New single plan 11/17/yyyy 80 RAN001 Firm
11/17/yyyy 90 RAN002 Firm
11/19/yyyy 90 RAN003 Firm
11/21/yyyy 100 Planned
11/24/yyyy 120 Planned
11/25/yyyy 130 Planned

All of the three firm requirements remain unchanged and are copied to the new single plan. The first planned requirement from the old single plan on 11/20/yyyy is scheduled before the latest planned requirement of the new schedule on 11/21/yyyy. Therefore, it is not copied to the new single plan. Instead, the new single plan now shows the planned requirements according to the new schedule. The requirement dates are 11/21/yyyy and 11/24/yyyy. The planned requirement on 11/25/yyyy remains unchanged and is copied to the new single plan.

In this example, the old single plan consists of two firm requirements and three planned requirements. A new schedule is received that contains two firm requirements:

Schedule Requirement date Requirement quantity RAN Type
Old single plan 11/17/yyyy 100 RAN001 Firm
11/17/yyyy 90 RAN002 Firm
11/19/yyyy 110 Planned
11/20/yyyy 120 Planned
11/25/yyyy 130 Planned
New schedule 11/17/yyyy 80 RAN001 Firm
11/19/yyyy 90 RAN003 Firm
New single plan 11/17/yyyy 80 RAN001 Firm
11/17/yyyy 90 RAN002 Firm
11/19/yyyy 90 RAN003 Firm
11/20/yyyy 120 Planned
11/25/yyyy 130 Planned

The first firm requirement quantity with RAN001 scheduled on 11/17/yyyy is adjusted from 100 to 80. The second firm requirement remains the same. The originally planned requirement quantity of 110 scheduled on 11/19/yyyy is replaced by a firm requirement. The firm requirement has the quantity 90 and RAN003 in the new single plan. The two planned requirements on 11/20/yyyy and on 11/25/yyyy remain unchanged and are copied to the new single plan.